APPROXIMATE APPLICATION PROCESSING TIMES

Conditional Use Permit – 10-12 weeks

General Plan Amendment 5-8  months

Environmental Impact Reports 8 - 12 months

Plan Checking/Building Permits 6 - 8 weeks

Site Plan Review 6-8 weeks

Tentative Tracts 4-6 months

Variance 3 months

Zone Change 4-6 months

Development Agreement 4-6 months